Once it's all configured, works great

The products work well, and all the parts are there. The problems are in the tolerances. When I have to use my own wire. US NEC says to use a number 6 wire for the grid wire coming in. It physically will not fit! I ended up cutting one strand out of that wire. Also the paper instruction manual is almost worthless. Youtube added the note on how to change the settings to allow two inverters to work in parallel. Have to turn the rocker switch off first! But I've been totally off grid now for a year. And I have electric water heater, AC, electric stove, and geothermal heat pumps. I've only had to use the generator 3 times.